Sync already completed issues using a trigger

Originally asked by Ziad Qadora on 03 August 2021 (original question)


Hello,

I have a trigger that basically will any issue created in the projects to the remote porject. When I the bulk exalate the issues in the project, all issues gets synced. But the status is Backlog and not the actual status.

What is the way to get the status of the remote issue to match the local status?

Regards,

Ziad


Answer by Ziad Qadora on 03 August 2021

MAde change to the sync rules status sycn then running Bulk sync again seems to have solved the issue