How to use Field's value to trigger a sync up?

Originally asked by allenhsieh on 16 November 2020 (original question)


Hi Supports,

Is it possible that we can trigger a sync up not by project = XXX, or issuetype = XXX, but by field’s value?


Answer by Michiel Meurs on 16 November 2020

Hi allenhsieh,

Yes, this is possible. If it can be entered in a JQL Query, it is totally possible.


Comments:

allenhsieh commented on 17 November 2020

Hi Michie,
Can you please show me the rope of how it can be done?
For instance, my field is called “working team” of which it has 4 values - A team, B team, C team, and D team.

How the JQL query shall be written?