Epic - Story syncing recomendation

Originally asked by Lara LG on 29 December 2020 (original question)


Hello,

I would like to know the best way to approach this, because I see similar questions but not the same use case.

I am syincing two projects with Epics and Stories.

When I create Epic AAA-10 it syncs with project BBB-1.

Now I want to sync Story AAA-22, which in project AAA belongs to Epic AAA-10, when I sync, the Story BBB-2 gets created BUT because the Epic Link is synced also story BBB-2 gets linked with epic AAA-10 instead of BBB-1.

To summarize, in two projects synced, Stories get linked to the source project Epic instead of the Epic of the destiny project. How can I fix the destiny project so that the stories get the information from the destiny Epic?

Thanks!


Answer by Francis Martens (Exalate) on 05 January 2021

Ah - this is a local sync.
What you would need to do in the incoming sync whenever exalating AAA-22 is lookup the twin of the parent epic (in this case BBB-1) and assign it to the epic link field of BBB-2

The details are available in How to sync epics in Jira Server

Let me know if you find the details.

Francis


Answer by Lara LG on 08 January 2021

Thanks Francis! It looks like what I need, I will test it.

Best Regards