Initial Sync of existing Sprints

Originally asked by Harold Oconitrillo on 15 March 2022 (original question)


Deat Idalko Team,

currently working on syncing an agile board (from a server instance to a cloud instance)
I manage to get created/updated sprint on local side, created/updated on remote side.
Would now like to make an already running project, accessible on the remote side. Thus: would also like to get the existing issues and sprints on the local side, initially created on the remote side.
How to organize this ?


Comments:

Harold Oconitrillo commented on 18 March 2022

Hi,

My advice to you is to set up a trigger query that matches the local project, then use the bulk Exalate operation to replicate on the remote end. Also, you may be interested to review as below.

https://docs.idalko.com/exalate/x/YZArAQ

Do not hesitate to contact us back for further questions.

Kind regards,

Harold Cruz

Answer by Stefan Albrecht on 22 March 2022

Hi,

tested this and it works. What initially was making me concerned that if I enter the Bulk Exalte option, is reporting a high amount of sprints to be sync (obviously from the complete system but not solely linked to the conrete project that is defined in the filter). Outgoing rule has a board related “if” clause. Important is, that not the data of other sprints are made “available” to the remot side.