Hi There,

I want to sync subtasks of two different projects. If I make changes in one subtask it should get sync with another subtask locally only.

Is it possible to do this using Exalate?


Answer by Juan Grases on 14 March 2020

Hi Vendant,

Sure it’s possible, you can follow this guide:

https://docs.idalko.com/exalate/display/ED/How+to+synchronize+tasks+and+subtasks

Best regards,