# Initial Sync of existing Sprints

**URL:** <https://community.exalate.com/t/initial-sync-of-existing-sprints/5114>\
**Category:** General Questions\
**Tags:** exalate, jira-cloud, jiracloud, migrated\_question, sync-sprint\
**Created:** [November 4, 2024, 7:44am UTC](https://community.exalate.com/t/initial-sync-of-existing-sprints/5114 "2024-11-04T07:44:21Z")\
**Posts on this page:** 2\
**Page:** 1

<div class="post-metadata">

**Author:** ![xl8bot](https://dub1.discourse-cdn.com/flex018/user_avatar/community.exalate.com/xl8bot/32/324_2.png) [@xl8bot](https://community.exalate.com/u/xl8bot)\
**Post date:** [November 4, 2024, 7:44am UTC](https://community.exalate.com/t/initial-sync-of-existing-sprints/5114/1 "2024-11-04T07:44:21Z")

</div>

_Originally asked by Harold Oconitrillo on 15 March 2022 [(original question)](https://oldcommunity.exalate.com/questions/42834816)_

* * *

Deat Idalko Team,

currently working on syncing an agile board (from a server instance to a cloud instance)  
I manage to get created/updated sprint on local side, created/updated on remote side.  
Would now like to make an already running project, accessible on the remote side. Thus: would also like to get the existing issues and sprints on the local side, initially created on the remote side.  
How to organize this ?

* * *

#### Comments:

> **Harold Oconitrillo commented on 18 March 2022**
>
> > Hi,
> 
> My advice to you is to set up a trigger query that matches the local project, then use the bulk Exalate operation to replicate on the remote end. Also, you may be interested to review as below.
> 
> [https://docs.idalko.com/exalate/x/YZArAQ](https://docs.idalko.com/exalate/x/YZArAQ)
> 
> Do not hesitate to contact us back for further questions.
> 
> Kind regards,
> 
> Harold Cruz

---

<div class="post-metadata">

**Author:** ![xl8bot](https://dub1.discourse-cdn.com/flex018/user_avatar/community.exalate.com/xl8bot/32/324_2.png) [@xl8bot](https://community.exalate.com/u/xl8bot)\
**Post date:** [November 4, 2024, 7:44am UTC](https://community.exalate.com/t/initial-sync-of-existing-sprints/5114/2 "2024-11-04T07:44:22Z")

</div>

_Answer by Stefan Albrecht on 22 March 2022_

Hi,

tested this and it works. What initially was making me concerned that if I enter the Bulk Exalte option, is reporting a high amount of sprints to be sync (obviously from the complete system but not solely linked to the conrete project that is defined in the filter). Outgoing rule has a board related “if” clause. Important is, that not the data of other sprints are made “available” to the remot side.

* * *