1
0
-1

Deat Idalko Team,

currently working on syncing an agile board (from a server instance to a cloud instance)
I manage to get created/updated sprint on local side, created/updated on remote side.
Would now like to make an already running project, accessible on the remote side. Thus: would also like to get the existing issues and sprints on the local side, initially created on the remote side.
How to organize this ?

  1. Harold Oconitrillo

    Hi,

    My advice to you is to set up a trigger query that matches the local project, then use the bulk Exalate operation to replicate on the remote end. Also, you may be interested to review as below.

    https://docs.idalko.com/exalate/x/YZArAQ 

    Do not hesitate to contact us back for further questions.

    Kind regards,

    Harold Cruz


CommentAdd your comment...

1 answer

  1.  
    2
    1
    0

    Hi,

    tested this and it works. What initially was making me concerned that if I enter the Bulk Exalte option, is reporting a high amount of sprints to be sync (obviously from the complete system but not solely linked to the conrete project that is defined in the filter). Outgoing rule has a board related "if" clause. Important is, that not the data of other sprints are made "available" to the remot side. 

      CommentAdd your comment...